ROADSIDE REVEGETATION—An Integrated Approach to Establishing Native Plants

CTIP

Initiation

Timeline

  1. The tri-agency (for a forest service road, this includes the local state DOT, the Forest Service, and WFLHD) calls for project proposals.
  2. Tri-agency discusses and ranks each project proposal
  3. Project identification report (PIR) is developed
  4. Road projects are selected
  5. Cross-functional team is formed, which includes a revegetation specialist
  6. Data collection and site surveys are conducted by revegetation specialist
  7. Findings from surveys are discussed and reported in the reconnaissance report